Light and Inspiration in Bristol
Light and Inspiration in Bristol

RWA

Bristol

Renovation of Grade II* listed building

THE PROJECT

The transformation of the heritage project was to revive and preserve it for the future. This has been the most significant refurbishment of the building in over a century.

The refurbished RWA now has a more inclusive space range from a new lift that can carry four wheelchair users and their careers, a quiet room for visitors with sensory requirements or autism and a family activity space.

There is a dedicated changing places facility so that people with profound and severe disabilities can "enjoy art on equal terms". As well as making the space more inclusive, the extensive restoration project has addressed urgent structural repairs.

One of the main tasks was to create new roof lanterns above the main gallery, as well as lowering the windows on the façade to create new doorways, adding air source heat pumps and installing new underfloor heating.

Visitors can now look forward to using the renovated café with 50 covers and outdoor seating spilling out onto a newly landscaped plaza.

Renovations have been funded by private donations and grants from the National Lottery Heritage Fund and Arts Council England, among others.

We are really pleased with the end result of the gallery and have had overwhelmingly positive feedback from our visitors. The entire Beard team have been a pleasure to work with from start to finish. They were welcoming when we came on site, accommodating of our requests, prompt to respond to any queries and thoroughly professional throughout.

Nicola Prosser

Director of Operations, The Royal West of England Academy

£3.1M

CONTRACT VALUE

49 WEEKS

CONTRACT DURATION

Customer

The Royal West 

of England Academy

Architect

Child & Sulzmann Partnership

Quantity Surveyor

Rider Levett Bucknall

Form of Contract

JCT Standard

CHALLENGES

  • Rock was found at the side of the building which meant we had to stop the original designed temporary works of the sheet piles being installed
  • Logistically challenging site, with the forecourt being installed the same time as the other works being undertaken
  • The local college was fully operational on the floor below the gallery, rooflights were removed which meant we had to ensure that there was full weathering in place at all times, without water ingress into the rooms below

SOLUTIONS

When rock was encountered on the project, we engaged with Craddy's to undertake a bespoke temporary works design which involved bracing steel from the existing building back up to the retaining wall of the church next door.

Logistical challenges were overcome by having a number of cranes lifting plant and equipment to undertake the install of the lift shaft, all deliveries were booked in 48 hours in advance to allow for the cranes or pallet trucks to be in place.

Only a section of the roof light was removed at one time. The scaffold which was installed was bunded with plastic to capture water ingress. The weathering was removed in the morning and installed in the evening if the glazing hadn't been installed in the mean time. Both roof lights were removed and replaced with only minimal water ingress.