THE PROJECT
Prior to Beard beginning work, the original structures were demolished and the concrete slab was removed. This has since been recycled on-site and used as aggregate material for under the building footprint and the hard landscaped areas.
£3.5M
CONTRACT VALUE
44 WEEKS
CONTRACT DURATION
Customer
University of Reading
Architect
Ridge & Partners
Procurement Route
Procurement
Partnership
Form of Contract
2 Stage, Negotiated
The new pavilion is constructed using steel frame and both internal blockwork and external brickwork.
The building is finished with a single ply roof and photovoltaic solar panels. The new pavilion provides changing rooms, a large function room and a kitchen/bar.
Externally the grounds include two football pitches and a full-size cricket pitch.